Overhead power line proposed from Kergord towards Sullom Voe.
Northern Shetland 220kV To Kergord 132kV
Free preview. £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- New-Build & Major Development
- Large 7/10
- Electrical Infrastructure
- Overhead Utility Lines
- Substation
Overview
Why it’s worth watching
A 220kV overhead line upgrade linking Kergord substation past Voe to a proposed northern substation near Sullom Voe Terminal is a significant infrastructure proposal affecting a wide area.
- Today
- An existing 132kV substation at Kergord is identified.
- Proposed
- An overhead line to a proposed 220kV northern substation near Sullom Voe Terminal.
- Size
- 132 kV existing substation · 220 kV proposed substation
- Stage
- Decided on 30 Oct 2025: Offer observations.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The application proposes an overhead line from the existing Kergord 132kV substation, past Voe, to a proposed 220kV northern substation near Sullom Voe Terminal. The council’s record says “Offer observations”; it does not give a final planning decision.
Written with AI from the application form and the council record.
Keep reading
Official records · analysis in progress
380 of 380 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.
Proposals and decisions come from Shetland Islands Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application SHE/2025/252/ECUCON?
Follow it on City Scope. This page is checked against the Shetland Islands Council planning register and shows the latest status, decision and documents for SHE/2025/252/ECUCON. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the Shetland Islands Council planning portal.
Set up a planning alertOn the street
What neighbours would notice.
- 01
An overhead line would run past Voe towards a proposed northern substation near Sullom Voe Terminal.
Tags
- Electrical Infrastructure
- Overhead Utility Lines
- Substation
What each tag is based on
- Electrical Infrastructure
- “220kV northern substation”
- Overhead Utility Lines
- “run overhead line from the existing Kergord 132kV substation”, “132kV line proposed”
- Substation
- “proposed 220kV northern substation”
All documents (4)
Where it’s at
The council has decided on 30 October 2025.
- Received23 Sept 2025
- Validated23 Sept 2025The council has everything it needs.
- Comments closed14 Oct 2025Usual deadline. Late comments may still count.
- Target decision23 Nov 20252-month target for local developments.
- Decision30 Oct 2025Offer observations.
The record
- Reference
- SHE/2025/252/ECUCON
- Address
- Northern Shetland 220kV To Kergord 132kV
- Status
- Unknown
- Council decision
- Offer observations
- Decision issued
- Category
- New-Build & Major Development
- Impact scale
- 7/10
- Authority
- Shetland Islands Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion