Planning applicationSHE/2025/252/ECUCON

Northern Shetland 220kV To Kergord 132kV

UnknownWorth watchingNew-Build & Major Development
Official records · analysis in progress

380 of 380 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.

Proposals and decisions come from Shetland Islands Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

23 September 2025

Validated

23 September 2025

Planning Signals

3 detected traits

Specific
Electrical InfrastructureOverhead Utility LinesSubstation
AI summary

Overhead 132kV line proposed past Voe to connect with a new nearby 220kV northern substation near Sullom Voe Terminal.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application SHE/2025/252/ECUCON

Northern Shetland 220kV To Kergord 132kV

UnknownNew-Build & Major DevelopmentReceived Shetland Islands Council

Overhead 132kV line proposed past Voe to connect with a new nearby 220kV northern substation near Sullom Voe Terminal.

Reference
SHE/2025/252/ECUCON
Address
Northern Shetland 220kV To Kergord 132kV
Status
Unknown
Category
New-Build & Major Development
Impact scale
7/10
Authority
Shetland Islands Council
Received
Validated
Last scraped
Record created

Plain-language summary

Overhead 132kV line proposed past Voe to connect with a new nearby 220kV northern substation near Sullom Voe Terminal.

As filed with the council

To run overhead line from the existing Kergord 132kV substation past Voe and onto a proposed 220kV northern substation near to Sullom Voe Terminal.