Planning applicationSHE/2025/279/ECUCON

Northern Shetland 220kV To Kergord 132kV

UnknownWorth watchingTelecommunications
Official records · analysis in progress

380 of 380 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.

Proposals and decisions come from Shetland Islands Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
Received

27 October 2025

Validated

27 October 2025

Planning Signals

5 detected traits

Specific
Associated InfrastructureElectricity Distribution Voltage Upgrade 11kvOverhead Line Double Circuit Schedule 8Overhead Utility LinesSection 37 Consent
Application Insights

No form insights available yet.

AI summary

Proposed overhead line linking North of Kergord Converter Station, running along A970 then A968 towards Toft/Scatsta.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application SHE/2025/279/ECUCON

Northern Shetland 220kV To Kergord 132kV

UnknownTelecommunicationsReceived Shetland Islands Council

Proposed overhead line linking North of Kergord Converter Station, running along A970 then A968 towards Toft/Scatsta.

Reference
SHE/2025/279/ECUCON
Address
Northern Shetland 220kV To Kergord 132kV
Status
Unknown
Category
Telecommunications
Impact scale
6/10
Authority
Shetland Islands Council
Received
Validated
Last scraped
Record created

Plain-language summary

Proposed overhead line linking North of Kergord Converter Station, running along A970 then A968 towards Toft/Scatsta.

As filed with the council

To run overhead line between North of Kergord Converter Station running generally parallel to the A970 before passing Voe and running alongside the A968 towards the Toft / Scatsta area.