Substation proposed south of Voe.

Land South Of Voe and West Of The A970 and East Of The Burn Of Voxter In The Vicinity Of Hamarigrind Mainland Shetland

Shetland Islands Council

Preview alerts near this site

Free preview. £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
New-Build & Major Development
Scale
Large 7/10
Tags
  • Access Roads
  • Associated Infrastructure
  • Associated Works
  • Civil Works
  • Drainage Wastewater Infrastructure

Overview

Why it’s worth watching

Major infrastructure project with clear public consequence and substantial scale.

Proposed
A 220/132 kV substation, with associated earthworks, platforms, drainage and access.
Size
220 /132 kV substation voltage
Stage
Decided on 19 Jun 2026: Proposal of Application Notice.

The council writes only to properties within 20 metres of an application site. Who is told

Site plan

In plain English

The application concerns the construction and operation of a 220/132 kV substation. It also describes earthworks, platforms, drainage, access and other associated works.

Written with AI from the application form and the council record.

Keep reading

Official records · analysis in progress

380 of 380 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.

Proposals and decisions come from Shetland Islands Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register

Track this application

How do I track planning application SHE/2026/115/PAN?

Follow it on City Scope. This page is checked against the Shetland Islands Council planning register and shows the latest status, decision and documents for SHE/2026/115/PAN. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the Shetland Islands Council planning portal.