Planning application · SHE/2026/120/ECUCON
Consultation on Northern Shetland to Kergord power line route options.
Between North Of Kergord Converter Station Running Generally Parallel To The A970 Before Passing Voe and Running Alongside The A968 Towards The Toft / Scatsta Area
Free preview. £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- Telecommunications
- Large 8/10
- Associated Infrastructure
- Associated Works
Overview
Why it’s worth watching
This pre-application consultation for a large-scale electricity transmission line indicates substantial development affecting a broad area, warranting prominent coverage.
- Proposed
- Alignment options for a Northern Shetland to Kergord transmission connection
- Stage
- Decided on 25 Jun 2026: Pre-app Complete.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
This is a pre-application consultation notification about alignment options for a proposed transmission connection from Northern Shetland to Kergord. The area described runs from north of Kergord Converter Station, generally parallel to the A970 before passing Voe, then alongside the A968 towards Toft / Scatsta. The record says the pre-application stage is complete.
Written with AI from the application form and the council record.
Keep reading
Official records · analysis in progress
380 of 380 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.
Proposals and decisions come from Shetland Islands Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application SHE/2026/120/ECUCON?
Follow it on City Scope. This page is checked against the Shetland Islands Council planning register and shows the latest status, decision and documents for SHE/2026/120/ECUCON. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the Shetland Islands Council planning portal.
Set up a planning alertThe impact
What it involves.
Tags
- Associated Infrastructure
- Associated Works
What each tag is based on
- Associated Infrastructure
- “ai_summary: "SSEN alignment options for a new 220kV transmission route"”
- Associated Works
- “ai_summary: "cable route alternatives shown"”
As lodged
The drawings.
Where it’s at
The council has decided on 25 June 2026.
- Received3 Jun 2026
- Validated3 Jun 2026The council has everything it needs.
- Comments closed24 Jun 2026Usual deadline. Late comments may still count.
- Target decision3 Aug 20262-month target for local developments.
- Decision25 Jun 2026Pre-app Complete.
Planning terms
- Pre-application advice
- Informal feedback from council planners before an application is lodged. It doesn't bind the final decision.
The record
- Reference
- SHE/2026/120/ECUCON
- Address
- Between North Of Kergord Converter Station Running Generally Parallel To The A970 Before Passing Voe And Running Alongside The A968 Towards The Toft / Scatsta Area
- Status
- Unknown
- Council decision
- Pre-app Complete
- Decision issued
- Category
- Telecommunications
- Impact scale
- 8/10
- Authority
- Shetland Islands Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.