Timeline changes

Active Travel Programme Timeline Changes

Edinburgh Council: 03 Feb 2026 vs June 2026. We flag projects where the construction start date moved later.

Compare from

Starts delayed

21

Construction start moved later

Biggest delay

1y 3m

West Edinburgh Link - Phase 4 – South Gyle Crescent; Broadway; Flassches Yard

Ends delayed

22

Construction end moved later

Average delay

1.5m

Positive start delays averaged across 51 matched projects

Sort
Red = laterGreen = earlierGrey = no changeDates are month-year from the council PDFs.
About this comparison

Projects are matched by name and phase. If a project was renamed between snapshots, it may show up as new or missing.

If something looks surprising, use the Open PDF buttons above to double-check the source.

Kingsknowe Park Crossing

Project explanation

A planned crossing project at Kingsknowe Park, listed in the council active travel programme for future construction.

Dedicated project detail was not found; the official programme confirms name, timing and status.

Source: Active Travel Improvements Programme January 2026

03 Feb 2026

StartSep 2026toEndOct 2026

Construction for this project has not yet started

June 2026

StartSep 2026toEndOct 2026

Construction for this project has not yet started

No change

West Edinburgh Link

PhasePhase 2 – Bankhead Avenue; Calder Road; Sighthill Road
Project explanation

A west Edinburgh route improving walking, wheeling and cycling links between The Gyle, Bankhead, South Gyle, Sighthill and Wester Hailes.

Source: West Edinburgh Link
delayed start

03 Feb 2026

StartJun 2026toEndDec 2026

Construction for this project has not yet started

June 2026

StartOct 2026toEndMay 2027

Construction for this project has not yet started

Delayed4m

Bughtlin Burn Bridge

Project explanation

A planned active travel bridge project listed in Edinburgh's active travel improvements programme.

The programme source gives status and timing, with limited scope detail.

Source: Active Travel Improvements Programme January 2026
delayed start

03 Feb 2026

StartSep 2026toEndOct 2026

Construction for this project has not yet started

June 2026

StartNov 2026toEndJan 2027

Construction for this project has not yet started

Delayed2m

QuietRoute 9

PhasePhase 2: Site A
Project explanation

A phased Roseburn to South Gyle QuietRoute project improving junctions and links, with early work around Balgreen and Saughtonhall.

Source: Roseburn to South Gyle walking, wheeling and cycling improvements
delayed start

03 Feb 2026

StartMar 2026toEndSep 2026

Construction for this project has not yet started

June 2026

StartNov 2026toEndJan 2027

Construction for this project has not yet started

Delayed8m

QuietRoute 9

PhasePhase 2: Site B
Project explanation

A phased Roseburn to South Gyle QuietRoute project improving junctions and links, with early work around Balgreen and Saughtonhall.

Source: Roseburn to South Gyle walking, wheeling and cycling improvements
delayed start

03 Feb 2026

StartJul 2026toEndSep 2026

Construction for this project has not yet started

June 2026

StartNov 2026toEndJan 2027

Construction for this project has not yet started

Delayed4m

Roseburn Path – Union Canal

PhaseDuff Street Lane Access Construction
Project explanation

Constructed Roseburn Path to Union Canal works forming part of the green corridor route, including crossing and access packages.

This appears to be a programme-name variant for Roseburn to Union Canal construction packages.

Source: Active Travel Improvements Programme January 2026
delayed start

03 Feb 2026

StartOct 2026toEndDec 2026

Construction for this project has not yet started

June 2026

StartNov 2026toEndJan 2027

Construction for this project has not yet started

Delayed1m

Travelling Safely buildouts improvements

PhasePhase 2: Morningside Road
Project explanation

A programme converting selected temporary Travelling Safely street changes into constructed improvements.

Programme source gives phases and status, with limited design detail.

Source: Active Travel Improvements Programme January 2026
delayed start

03 Feb 2026

StartJun 2026toEndAug 2026

Construction for this project has not yet started

June 2026

StartNov 2026toEndJan 2027

Construction for this project has not yet started

Delayed5m

Fillyside Crossing

Project explanation

A crossing intended to connect Fillyside Road with Seafield promenade for people walking and cycling.

Official sources confirm the project name; this source gives the clearest public description found.

Source: Active Travel Action Plan 2030
delayed start

03 Feb 2026

StartNov 2026toEndDec 2026

Construction for this project has not yet started

June 2026

StartJan 2027toEndMar 2027

Construction for this project has not yet started

Delayed2m

One-way Street Exemptions

PhaseBatch 2
Project explanation

Contraflow cycling exemptions on selected one-way streets to improve cycle network connectivity and road safety.

Source: Statement of Reasons - One-Way Street Exemptions

03 Feb 2026

StartJan 2027toEndFeb 2027

Construction for this project has not yet started

June 2026

StartJan 2027toEndFeb 2027

Construction for this project has not yet started

No change

One-way Street Exemptions

PhaseBatches 3, 4 & 5
Project explanation

Contraflow cycling exemptions on selected one-way streets to improve cycle network connectivity and road safety.

Source: Statement of Reasons - One-Way Street Exemptions

03 Feb 2026

StartMar 2027toEndMay 2027

Construction for this project has not yet started

June 2026

StartMar 2027toEndMay 2027

Construction for this project has not yet started

No change

West Edinburgh Link

PhasePhase 3 – Wester Hailes Road; Murrayburn
Project explanation

A west Edinburgh route improving walking, wheeling and cycling links between The Gyle, Bankhead, South Gyle, Sighthill and Wester Hailes.

Source: West Edinburgh Link

03 Feb 2026

StartJul 2027toEndFeb 2028

Construction for this project has not yet started

June 2026

StartMar 2027toEndApr 2028

Construction for this project has not yet started

Earlier4m

Cameron Toll to BioQuarter general scheme

Project explanation

A walking and cycling route improvement between Cameron Toll and Edinburgh BioQuarter.

Source: Cameron Toll to BioQuarter walking and cycling route
delayed start

03 Feb 2026

StartDec 2026toEndOct 2027

Construction for this project has not yet started

June 2026

StartApr 2027toEndFeb 2028

Construction for this project has not yet started

Delayed4m

Meadows to Union Canal

PhasePhase 1b - Tarvit St.
Project explanation

Improves walking, wheeling and cycling between the Meadows and Union Canal along NCN75, including safer journeys and better public spaces.

Source: Meadows to Union Canal

03 Feb 2026

StartApr 2027toEndNov 2027

Construction for this project has not yet started

June 2026

StartApr 2027toEndNov 2027

Construction for this project has not yet started

No change

QuietRoute 30 - Dalkeith Road to Ratcliffe Terrace

Project explanation

A QuietRoute scheme to improve walking and cycling between Holyrood Park, Dalkeith Road and Ratcliffe Terrace.

Source: Holyrood Park to Ratcliffe Terrace consultation summary
delayed start

03 Feb 2026

StartMar 2027toEndMay 2027

Construction for this project has not yet started

June 2026

StartApr 2027toEndJul 2027

Construction for this project has not yet started

Delayed1m

Smokey Brae

Project explanation

A project to make Smokey Brae and Marionville safer and more attractive for walking, wheeling and cycling.

Source: Smokey Brae and Marionville
delayed start

03 Feb 2026

StartMar 2027toEndAug 2027

Construction for this project has not yet started

June 2026

StartMay 2027toEndOct 2027

Construction for this project has not yet started

Delayed2m

Cultins Road Shared Footway

Project explanation

A shared footway scheme involving widening, resurfacing and crossing upgrades on Cultins Road.

Older committee papers provide clearer scope than later programme listings.

Source: 8% Budget Commitment to Cycling
delayed start

03 Feb 2026

StartApr 2027toEndJul 2027

Construction for this project has not yet started

June 2026

StartJun 2027toEndAug 2027

Construction for this project has not yet started

Delayed2m

Longstone Link

PhasePhase 1 – Bridge
Project explanation

A planned active travel bridge route at Longstone, with Phase 1 focused on the Inglis Green Bridge route.

The broader project scope may evolve beyond the Phase 1 bridge route.

Source: City Plan 2030 Delivery Programme January 2025

03 Feb 2026

StartJun 2027toEndMay 2028

Construction for this project has not yet started

June 2026

StartJun 2027toEndMay 2028

Construction for this project has not yet started

No change

Meadows to George Street

Project explanation

Transforms walking, cycling, accessibility and public spaces on busy streets linking the Meadows with George Street.

Source: Meadows to George Street - Streets for People
delayed start

03 Feb 2026

StartMar 2027toEndAug 2028

Construction for this project has not yet started

June 2026

StartJun 2027toEndAug 2027

Construction for this project has not yet started

Delayed3m

Queensferry Connections

Project explanation

A package of active travel improvements across Queensferry, including Builyeon Road, Echline Interchange and Ferry Muir Road links.

Source: Queensferry active travel links
delayed start

03 Feb 2026

StartMay 2027toEndJul 2029

Construction for this project has not yet started

June 2026

StartJun 2027toEndSep 2027

Construction for this project has not yet started

Delayed1m

Rural Speed Limits

Project explanation

A road-safety project reducing speed limits on rural roads to make walking, cycling and horse riding less intimidating.

Source: Speed Limits Review: 20mph and Rural Roads
delayed start

03 Feb 2026

StartApr 2027toEndJun 2027

Construction for this project has not yet started

June 2026

StartJun 2027toEndAug 2027

Construction for this project has not yet started

Delayed2m

LDPAP - Leith Connections

PhasePhase 3: Hawthornvale to Seafield
Project explanation

Phase 3 of Leith Connections, proposing walking, cycling and public realm improvements between Hawthornvale Path and Seafield.

Source: Leith Connections Phase 3 Engagement Report

03 Feb 2026

StartJul 2027toEndDec 2028

Construction for this project has not yet started

June 2026

StartJul 2027toEndDec 2028

Construction for this project has not yet started

No change

St Andrew Square

Project explanation

A planned active travel project at St Andrew Square, listed in Edinburgh's programme for future construction.

Programme sources give timing but limited scope detail.

Source: Active Travel Improvements Programme January 2026

03 Feb 2026

StartAug 2027toEndFeb 2028

Construction for this project has not yet started

June 2026

StartAug 2027toEndFeb 2028

Construction for this project has not yet started

No change

Dalry Town Centre

Project explanation

Town centre proposals to make Dalry greener and safer with wider pavements, better cycling provision and improved junctions.

Source: Consultation opens on future Dalry town centre proposals

03 Feb 2026

StartSep 2027toEndMay 2028

Construction for this project has not yet started

June 2026

StartSep 2027toEndMay 2028

Construction for this project has not yet started

No change

Granton Liveable Neighbourhood

Project explanation

A future liveable-neighbourhood project in Granton, listed in the City Mobility Plan delivery pipeline and active travel programme.

Dedicated public project detail appears limited.

Source: Delivering the City Mobility Plan

03 Feb 2026

StartSep 2027toEndNov 2027

Construction for this project has not yet started

June 2026

StartSep 2027toEndNov 2027

Construction for this project has not yet started

No change

Currie and Balerno Active Travel Improvements

Project explanation

Proposals focused on safer walking, wheeling and cycling access to Curriehill station, schools, shops and the medical centre.

Source: Walking, wheeling and cycling improvements in Currie

03 Feb 2026

StartOct 2027toEndJan 2028

Construction for this project has not yet started

June 2026

StartOct 2027toEndJan 2028

Construction for this project has not yet started

No change

George Street to Waverley Bridge

Project explanation

A future active travel project listed by the council between George Street and Waverley Bridge.

Dedicated project detail was not found; the official programme confirms name and status.

Source: Active Travel Improvements Programme January 2026

03 Feb 2026

StartDec 2027toEndDec 2028

Construction for this project has not yet started

June 2026

StartDec 2027toEndDec 2028

Construction for this project has not yet started

No change

NEAT Connections

Project explanation

Now called North Edinburgh Connections, proposing safer streets, accessible pavements, protected cycle lanes and better public spaces.

Source: North Edinburgh Connections
delayed start

03 Feb 2026

StartSep 2027toEndSep 2028

Construction for this project has not yet started

June 2026

StartJan 2028toEndDec 2028

Construction for this project has not yet started

Delayed4m

Barnton And Whitehouse Road Link To Ncn1

Project explanation

A Local Development Plan Action Programme project to connect Barnton and Whitehouse Road with National Cycle Network 1.

Public detail appears to be limited to programme and pipeline references.

Source: Delivering the City Mobility Plan
delayed start

03 Feb 2026

StartJan 2028toEndJun 2029

Construction for this project has not yet started

June 2026

StartFeb 2028toEndMay 2028

Construction for this project has not yet started

Delayed1m

Fountainbridge - Dundee Street

PhasePhase 1
Project explanation

Walking, wheeling and cycling improvements along Dundee Street, Fountainbridge and streets linking to the Union Canal.

Source: Dundee Street Fountainbridge Active Travel Project
delayed start

03 Feb 2026

StartJan 2028toEndMar 2028

Construction for this project has not yet started

June 2026

StartApr 2028toEndJul 2028

Construction for this project has not yet started

Delayed3m

West Edinburgh Link

PhasePhase 4 – South Gyle Crescent; Broadway; Flassches Yard
Project explanation

A west Edinburgh route improving walking, wheeling and cycling links between The Gyle, Bankhead, South Gyle, Sighthill and Wester Hailes.

Source: West Edinburgh Link
delayed start

03 Feb 2026

StartJan 2027toEndJul 2027

Construction for this project has not yet started

June 2026

StartApr 2028toEndOct 2028

Construction for this project has not yet started

Delayed1y 3m

Niddrie Mains Road

Project explanation

Craigmillar Niddrie Connections proposes safer crossings, bus lanes, cycle routes and improved public spaces along Niddrie Mains Road.

Source: Craigmillar Niddrie Connections
delayed start

03 Feb 2026

StartMay 2028toEndAug 2029

Construction for this project has not yet started

June 2026

StartJun 2028toEndMar 2031

Construction for this project has not yet started

Delayed1m

George Street and First New Town

Project explanation

A redesign of George Street and the First New Town with wider pavements, landscaped seating, active travel priority and a two-way cycleway.

Source: George Street and First New Town redesign
delayed start

03 Feb 2026

StartMar 2028toEndFeb 2030

Construction for this project has not yet started

June 2026

StartDec 2028toEndJan 2033

Construction for this project has not yet started

Delayed9m

Cameron Toll to BioQuarter general scheme

PhaseLady Road section
Project explanation

A walking and cycling route improvement between Cameron Toll and Edinburgh BioQuarter.

Source: Cameron Toll to BioQuarter walking and cycling route
delayed start

03 Feb 2026

StartJan 2029toEndApr 2029

Construction for this project has not yet started

June 2026

StartMay 2029toEndNov 2029

Construction for this project has not yet started

Delayed4m

Charlotte Square

PhasePhase 3. Permanent Scheme
Project explanation

A public realm enhancement intended to make Charlotte Square quieter, safer and more welcoming for walking, wheeling and cycling.

Source: Charlotte Square Public Realm Enhancement

03 Feb 2026

StartOct 2029toEndOct 2030

Construction for this project has not yet started

June 2026

StartOct 2029toEndOct 2030

Construction for this project has not yet started

No change

QuietRoute 9

PhasePhase 2: Site C
Project explanation

A phased Roseburn to South Gyle QuietRoute project improving junctions and links, with early work around Balgreen and Saughtonhall.

Source: Roseburn to South Gyle walking, wheeling and cycling improvements

03 Feb 2026

StartMar 2026toEndSep 2026

Construction for this project has not yet started

June 2026

StartMar 2026toEndJul 2026

Project is under construction

No change

Leith Connections

PhasePhase 2 - LTN
Project explanation

Street changes in Leith to reduce through traffic, create public spaces and improve walking, wheeling and cycling connections.

Source: Leith Connections

03 Feb 2026

StartFeb 2026toEndApr 2026

Project is under construction

June 2026

StartFeb 2026toEndApr 2026

This project has been constructed.

No change

One-way Street Exemptions

PhaseBatch 1
Project explanation

Contraflow cycling exemptions on selected one-way streets to improve cycle network connectivity and road safety.

Source: Statement of Reasons - One-Way Street Exemptions

03 Feb 2026

StartFeb 2026toEndApr 2026

Construction in progress

June 2026

StartFeb 2026toEndApr 2026

This project has been constructed.

No change

Meadows to Union Canal

PhaseKings Theatre
Project explanation

Improves walking, wheeling and cycling between the Meadows and Union Canal along NCN75, including safer journeys and better public spaces.

Source: Meadows to Union Canal

03 Feb 2026

StartJan 2026toEndApr 2026

Project is under construction

June 2026

StartJan 2026toEndApr 2026

This project has been constructed.

No change

Corstorphine Low Traffic Neighbourhood

Project explanation

A low traffic neighbourhood designed to create safer, more comfortable local streets for walking, cycling, wheeling and spending time.

Source: Corstorphine Connections Engagement Summary Report

03 Feb 2026

StartDec 2025toEndMar 2026

Project is under construction

June 2026

StartDec 2025toEndApr 2026

This project has been constructed.

No change

Dalry Town Centre

PhaseDalry Side Street Project
Project explanation

Town centre proposals to make Dalry greener and safer with wider pavements, better cycling provision and improved junctions.

Source: Consultation opens on future Dalry town centre proposals

03 Feb 2026

StartDec 2025toEndMar 2026

Project is under construction

June 2026

StartDec 2025toEndMar 2026

This project has been constructed.

No change

West Edinburgh Link

PhasePhase 1 Bankhead to South Gyle Access
Project explanation

A west Edinburgh route improving walking, wheeling and cycling links between The Gyle, Bankhead, South Gyle, Sighthill and Wester Hailes.

Source: West Edinburgh Link

03 Feb 2026

StartNov 2025toEndJun 2026

Project is under construction

June 2026

StartNov 2025toEndAug 2026

Project is under construction

No change

Travelling Safely buildouts improvements

PhasePhase 1: Portobello and St John's Road
Project explanation

A programme converting selected temporary Travelling Safely street changes into constructed improvements.

Programme source gives phases and status, with limited design detail.

Source: Active Travel Improvements Programme January 2026

03 Feb 2026

StartApr 2025toEndJun 2025

This project has been constructed.

June 2026

StartApr 2025toEndJun 2025

This project has been constructed.

No change

Leith Connections

PhasePhase 1a - Strategic Route
Project explanation

Street changes in Leith to reduce through traffic, create public spaces and improve walking, wheeling and cycling connections.

Source: Leith Connections

03 Feb 2026

StartNov 2024toEndDec 2025

This project has been constructed.

June 2026

StartNov 2024toEndDec 2025

This project has been constructed.

No change

Deanhaugh Street and Leslie Place

Project explanation

A junction improvement scheme to upgrade pedestrian crossings at Deanhaugh Street and Leslie Place.

Source: Approval of Appointment of Consultants to Design Cycling and Walking Schemes

03 Feb 2026

StartOct 2024toEndDec 2024

This project has been constructed.

June 2026

StartOct 2024toEndDec 2024

This project has been constructed.

No change

Charlotte Square

PhasePhase 2. Interim Scheme
Project explanation

A public realm enhancement intended to make Charlotte Square quieter, safer and more welcoming for walking, wheeling and cycling.

Source: Charlotte Square Public Realm Enhancement

03 Feb 2026

StartJun 2024toEndMar 2026

Project is under construction

June 2026

StartJun 2024toEndMay 2026

This project has been constructed.

No change

Melville Crescent

Project explanation

A project to reimagine Melville Crescent as a more pleasant environment for residents, workers and people passing through.

Source: Reimagining Melville Crescent

03 Feb 2026

StartApr 2024toEndDec 2024

This project has been constructed.

June 2026

StartApr 2024toEndDec 2024

This project has been constructed.

No change

QuietRoute 60 – Davidson's Mains Park

PhasePhase 2
Project explanation

Improvements to Davidson's Mains Park on QuietRoute 60, focused on widening and lighting the path from Queensferry Road to Barnton Avenue.

Source: Davidson's Mains Park Walk and Cycle Improvements

03 Feb 2026

StartApr 2024toEndMar 2025

This project has been constructed.

June 2026

StartApr 2024toEndMar 2025

This project has been constructed.

No change

Tram Safety Improvements

Project explanation

Cycle safety improvements along the existing Edinburgh Tram route to improve conditions for walking and cycling.

Source: Tram Route Cycle Safety Improvements

03 Feb 2026

StartApr 2023toEndMar 2024

This project has been constructed.

June 2026

StartApr 2023toEndMar 2024

This project has been constructed.

No change

Roseburn Path – Union Canal

Project explanation

Constructed Roseburn Path to Union Canal works forming part of the green corridor route, including crossing and access packages.

This appears to be a programme-name variant for Roseburn to Union Canal construction packages.

Source: Active Travel Improvements Programme January 2026

03 Feb 2026

StartMar 2023toEndFeb 2025

This project has been constructed.

June 2026

StartMar 2023toEndFeb 2025

This project has been constructed.

No change

Roseburn Path – Union Canal

PhaseDalry Road Toucan Installation
Project explanation

Constructed Roseburn Path to Union Canal works forming part of the green corridor route, including crossing and access packages.

This appears to be a programme-name variant for Roseburn to Union Canal construction packages.

Source: Active Travel Improvements Programme January 2026

03 Feb 2026

StartMar 2023toEndFeb 2025

This project has been constructed.

June 2026

StartMar 2023toEndFeb 2025

This project has been constructed.

No change

City Centre West East Link

Project explanation

A major cycling and walking route linking the east and west of Edinburgh city centre.

Source: City Centre West to East Link

03 Feb 2026

StartFeb 2022toEndFeb 2025

This project has been constructed.

June 2026

StartFeb 2022toEndFeb 2025

This project has been constructed.

No change