Existing overhead lines to be reconductored between Peterhead and Kintore.
Peterhead, Persley and Kintore
Free with a City Scope account. One email, when the council decides.
Also email me new applications nearby · £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- New-Build & Major Development
- Large 8/10
- Electrical Infrastructure
- Overhead Utility Lines
- Section 37 Consent
- Substation
Overview
Why it’s worth watching
This is a large strategic electricity transmission upgrade across multiple north-east locations with significant infrastructure implications.
- Today
- Existing 275 kV and 132 kV overhead lines.
- Proposed
- Reconductoring to enable operation at 400 kV and 275 kV, respectively.
- Size
- 400 kV proposed operating voltage, Peterhead–Kintore · 275 kV proposed operating voltage, Persley
- Stage
- Past its target date of 29 Jun 2026.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The application proposes reconductoring existing overhead lines. Approximately 51 kilometres (km) of a 275 kilovolt (kV) line between substations connecting Peterhead and Kintore would be enabled to operate at 400 kV. Approximately 12 km of a 132 kV line connecting Persley Tee to Persley Substation would be enabled to operate at 275 kV.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
1,000 of 1,158 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 158 records from that period are still being added or checked.
Proposals and decisions come from Aberdeen City Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application ABC/260495/S37?
Follow it on City Scope. This page is checked against the Aberdeen City Council planning register and shows the latest status, decision and documents for ABC/260495/S37. City Scope can email you when this application is decided, free with a City Scope account. To comment on the application, use the Aberdeen City Council planning portal.
On the street
What neighbours would notice.
- 01
Work is proposed on existing overhead lines connecting substations between Peterhead and Kintore.
- 02
Work is also proposed on the existing overhead line connecting Persley Tee to Persley Substation.
Tags
- Electrical Infrastructure
- Overhead Utility Lines
- Section 37 Consent
- Substation
What each tag is based on
- Electrical Infrastructure
- “Reconductoring of approximately 51 kilometres (km) of an existing 275 kilovolt (kV) overhead line”
- Overhead Utility Lines
- “existing 275 kilovolt (kV) overhead line (OHL)”, “existing 132 kV OHL”
- Section 37 Consent
- “reference_no 260495/S37”
- Substation
- “connecting substations between Peterhead and Kintore”, “Persley Substation”
As lodged
The drawings.
All documents (4)
On the map
Open the planning map →© MapTiler / OpenFreeMap © OpenStreetMap contributors
Where it’s at
Comments have closed. The target date for a decision has passed.
- Received29 Apr 2026
- Validated29 Apr 2026The council has everything it needs.
- Comments closed20 May 2026Usual deadline. Late comments may still count.
- Target decision (next)29 Jun 20262-month target for local developments.
- DecisionNot yet
The record
- Reference
- ABC/260495/S37
- Address
- Peterhead, Persley And Kintore
- Status
- Pending
- Category
- New-Build & Major Development
- Impact scale
- 8/10
- Authority
- Aberdeen City Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.