Planning applicationABS/APP/2025/1213

Land North Of Longside Road Flushing Peterhead Aberdeenshire

DecidedWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

1,742 of 1,898 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 156 records from that period are still being added or checked.

Proposals and decisions come from Aberdeenshire Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

24 July 2025

Validated

24 July 2025

Planning Signals

2 detected traits

Specific
Associated InfrastructureSection 36 Consent
AI summary

Proposed BESS battery storage site (up to 400MW) with associated grid and energy infrastructure works across farmland near existing power assets.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application ABS/APP/2025/1213

Land North Of Longside Road Flushing Peterhead Aberdeenshire

DecidedRenewable Energy, EV & Heat PumpsReceived Aberdeenshire Council

Proposed BESS battery storage site (up to 400MW) with associated grid and energy infrastructure works across farmland near existing power assets.

Reference
ABS/APP/2025/1213
Address
Land North Of Longside Road Flushing Peterhead Aberdeenshire
Status
Decided
Category
Renewable Energy, EV & Heat Pumps
Impact scale
8/10
Authority
Aberdeenshire Council
Received
Validated
Last scraped
Record created
Latitude
57.5155
Longitude
-1.9074

Plain-language summary

Proposed BESS battery storage site (up to 400MW) with associated grid and energy infrastructure works across farmland near existing power assets.

As filed with the council

Consultation under Section 36 of the Electricity Act 1989 for the Installation of Battery Energy Storage System (BESS) with an Installed Capacity of up to 400MW and Associated Infrastructure