Planning applicationABS/APP/2025/1262

Land Circa 200M West Of Greystone Peterhead Aberdeenshire AB42 3JP

DecidedWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

1,742 of 1,898 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 156 records from that period are still being added or checked.

Proposals and decisions come from Aberdeenshire Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

31 July 2025

Validated

31 July 2025

Planning Signals

2 detected traits

Specific
Associated InfrastructureSection 36 Consent
AI summary

Plans submitted for a large Battery Energy Storage System (BESS) up to 500MW with associated infrastructure under Section 36 consultation.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application ABS/APP/2025/1262

Land Circa 200M West Of Greystone Peterhead Aberdeenshire AB42 3JP

DecidedRenewable Energy, EV & Heat PumpsReceived Aberdeenshire Council

Plans submitted for a large Battery Energy Storage System (BESS) up to 500MW with associated infrastructure under Section 36 consultation.

Reference
ABS/APP/2025/1262
Address
Land Circa 200M West Of Greystone Peterhead Aberdeenshire AB42 3JP
Status
Decided
Category
Renewable Energy, EV & Heat Pumps
Impact scale
8/10
Authority
Aberdeenshire Council
Received
Validated
Last scraped
Record created
Latitude
57.473
Longitude
-1.8474

Plain-language summary

Plans submitted for a large Battery Energy Storage System (BESS) up to 500MW with associated infrastructure under Section 36 consultation.

As filed with the council

Consultation under Section 36 of the Electricity Act 1989 for the Installation of Battery Energy Storage System (BESS) with a Generating Capacity of up to 500MW and Associated Infrastructure