Planning applicationAGB/26/00134/LIB

Cruachan Power Station Lochawe Argyll And Bute PA33 1AN

DecidedInternal Works & Accessibility
Official records · coverage in progress

1,438 of 1,612 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 174 records from that period are still being added or checked.

Proposals and decisions come from Argyll and Bute Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 3
Received

23 January 2026

Validated

18 February 2026

Planning Signals

2 detected traits

Works
Windows & Doors
Specific
Fire Doors
Application Insights

No form insights available yet.

AI summary

Works at Cruach Power Station cavern complex to upgrade west/central/east stair security and fire doors, plus safety barrier improvements in the machine hall.

Impact scale

Estimated scale of impact on the surrounding area.

3/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application AGB/26/00134/LIB

Cruachan Power Station Lochawe Argyll And Bute PA33 1AN

DecidedInternal Works & AccessibilityReceived Argyll and Bute Council

Works at Cruach Power Station cavern complex to upgrade west/central/east stair security and fire doors, plus safety barrier improvements in the machine hall.

Reference
AGB/26/00134/LIB
Address
Cruachan Power Station Lochawe Argyll And Bute PA33 1AN
Status
Decided
Category
Internal Works & Accessibility
Impact scale
3/10
Authority
Argyll and Bute Council
Received
Validated
Last scraped
Record created
Latitude
56.4028
Longitude
-5.1131

Plain-language summary

Works at Cruach Power Station cavern complex to upgrade west/central/east stair security and fire doors, plus safety barrier improvements in the machine hall.

As filed with the council

Alterations to existing control block access to form new upgraded security doors at the west, central and east stairs. Replacement/upgrade of all existing fire doors. Alterations to replace existing protective barriers in machine hall and at lighting gantry to meet current safety requirements