Planning applicationAGB/26/00335/PP

Land East Of Kilmartin And North East Of Lochgilphead Argyll And Bute

Awaiting decisionWorth watchingLegal / Administrative
Official records · coverage in progress

1,438 of 1,612 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 174 records from that period are still being added or checked.

Proposals and decisions come from Argyll and Bute Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 3
Received

23 February 2026

Validated

25 February 2026

Planning Signals

2 detected traits

Specific
Section 42 VariationWind Turbine
Application Insights

No form insights available yet.

AI summary

Proposal to extend the time limit for completing grid connection works for the wind farm, varying a prior planning condition under Section 42.

Impact scale

Estimated scale of impact on the surrounding area.

1/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application AGB/26/00335/PP

Land East Of Kilmartin And North East Of Lochgilphead Argyll And Bute

Awaiting decisionLegal / AdministrativeReceived Argyll and Bute Council

Proposal to extend the time limit for completing grid connection works for the wind farm, varying a prior planning condition under Section 42.

Reference
AGB/26/00335/PP
Address
Land East Of Kilmartin And North East Of Lochgilphead Argyll And Bute
Status
Awaiting decision
Category
Legal / Administrative
Impact scale
1/10
Authority
Argyll and Bute Council
Received
Validated
Last scraped
Record created
Latitude
56.1444
Longitude
-5.3776

Plain-language summary

Proposal to extend the time limit for completing grid connection works for the wind farm, varying a prior planning condition under Section 42.

As filed with the council

Application under Section 42 of the Town and Country Planning (Scotland) Act 1997 to vary the Standard Time Condition Limit of application reference 22/01380/PP from three years to ten years to allow for completion of grid connection works to connect the wind farm