Proposed Divot Hill Wind Farm Site Land 7km To The North-east Of St John's Town Of Dalry Castle Douglas

Assessment StageWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

1,479 of 1,663 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 184 records from that period are still being added or checked.

Proposals and decisions come from Dumfries and Galloway Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 3
Received

27 January 2026

Validated

28 January 2026

Planning Signals

3 detected traits

Specific
Section 42 VariationWind Farm Micro Siting VariationWind Turbine
Application Insights

No form insights available yet.

AI summary

Plans would tweak the Divot Hill wind farm layout and turbine positions, with up to nine turbines and taller tips (around 220m).

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application DGY/26/0136/S42

Proposed Divot Hill Wind Farm Site Land 7km To The North-east Of St John's Town Of Dalry Castle Douglas

Assessment StageRenewable Energy, EV & Heat PumpsReceived Dumfries and Galloway Council

Plans would tweak the Divot Hill wind farm layout and turbine positions, with up to nine turbines and taller tips (around 220m).

Reference
DGY/26/0136/S42
Address
Proposed Divot Hill Wind Farm Site Land 7km To The North-east Of St John's Town Of Dalry Castle Douglas
Status
Assessment Stage
Category
Renewable Energy, EV & Heat Pumps
Impact scale
8/10
Authority
Dumfries and Galloway Council
Received
Validated
Last scraped
Record created
Latitude
55.1518
Longitude
-4.0706

Plain-language summary

Plans would tweak the Divot Hill wind farm layout and turbine positions, with up to nine turbines and taller tips (around 220m).

As filed with the council

ERECTION, 35-YEAR OPERATION AND SUBSEQUENT DECOMMISSIONING OF A WIND FARM COMPRISING UP TO NINE WIND TURBINES, INCLUDING ASSOCIATED INFRASTRUCTURE (AT VARIANCE WITH CONDITIONS 2 AND 12 OF PLANNING PERMISSION 23/0368/FUL TO ALLOW CHANGES TO TURBINE POSITIONS AND INFRASTRUCTURE LAYOUT OUTWITH THE CONSENTED MICROSITING ALLOWANCE AND TO ALLOW AN INCREASE IN TURBINE TIP HEIGHT FROM 200 METRES TO 220 METRES) (SECTION 42)