Planning applicationDGY/26/0353/FUL

Lockerbie Creamery Lockerbie DG11 1LW

Assessment StageWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

1,479 of 1,663 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 184 records from that period are still being added or checked.

Proposals and decisions come from Dumfries and Galloway Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 3
Received

27 February 2026

Validated

9 March 2026

Planning Signals

11 detected traits

Works
Boundary TreatmentLandscaping
Specific
Access RoadsAssociated InfrastructureCctv InstallationGround Mounted Solar Panels
Application Insights

No form insights available yet.

AI summary

Proposed 5MW ground-mounted solar farm with 2m perimeter fencing, CCTV masts, transformer/control buildings, access tracks, underground cabling and landscaping.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application DGY/26/0353/FUL

Lockerbie Creamery Lockerbie DG11 1LW

Assessment StageRenewable Energy, EV & Heat PumpsReceived Dumfries and Galloway Council

Proposed 5MW ground-mounted solar farm with 2m perimeter fencing, CCTV masts, transformer/control buildings, access tracks, underground cabling and landscaping.

Reference
DGY/26/0353/FUL
Address
Lockerbie Creamery Lockerbie DG11 1LW
Status
Assessment Stage
Category
Renewable Energy, EV & Heat Pumps
Impact scale
7/10
Authority
Dumfries and Galloway Council
Received
Validated
Last scraped
Record created
Latitude
55.1189
Longitude
-3.4153

Plain-language summary

Proposed 5MW ground-mounted solar farm with 2m perimeter fencing, CCTV masts, transformer/control buildings, access tracks, underground cabling and landscaping.

As filed with the council

CONSTRUCTION OF 5.0MW GROUND MOUNTED SOLAR FARM WITH INVERTERS, 2 METRE HIGH PERIMETER FENCING, 5 METRE HIGH POLE MOUNTED CCTV CAMERAS, SITING OF TRANSFORMER SUBSTATION, CONTROL ROOM, FORMATION OF ACCESS TRACKS, UNDERGROUND CABLING AND ASSOCIATED INFRASTRUCTURE, AND LANDSCAPE WORKS