Land 500M West Of DC Site Spittal Sub Station Halkirk
A proposed 162MW battery energy storage system at Achies, with associated infrastructure and grid connections.
The record
- Reference
- HLD/25/02382/S36
- Address
- Land 500M West Of DC Site Spittal Sub Station Halkirk
- Status
- Awaiting decision
- Category
- Renewable Energy, EV & Heat Pumps
- Impact scale
- 8/10
- Authority
- The Highland Council
Timeline
- Received
- Validated
- Last scraped
- Record created
Additional application data
- Latitude
- 58.4798
- Longitude
- -3.4606
What is proposed
Plain-language summary
A proposed 162MW battery energy storage system at Achies, with associated infrastructure and grid connections.
As filed with the council
Achies BESS - Construct and operate a battery energy storage system (BESS) development and associated infrastructure, with a generating capacity of approximately 162MW. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00006111