CityScope · Planning Updates
Application HLD/25/03986/S37
Land 1525M SE Of Finglack Culloden Moor Inverness
Proposed 400kV overhead line (~186km) between new substations near Beauly, New Deer and Peterhead, with steel towers, diversions and realignments.
The record
- Reference
- HLD/25/03986/S37
- Address
- Land 1525M SE Of Finglack Culloden Moor Inverness
- Status
- Decided
- Category
- New-Build & Major Development
- Impact scale
- 9/10
- Authority
- The Highland Council
Timeline
- Received
- Validated
- Last scraped
- Record created
What is proposed
Plain-language summary
Proposed 400kV overhead line (~186km) between new substations near Beauly, New Deer and Peterhead, with steel towers, diversions and realignments.
As filed with the council
Beauly to Peterhead 400 kV OHL - Install, operate and keep installed 186km of new 400 kV overhead transmission line (OHL), supported on steel lattice tower structures, between proposed new substations at Fanellan (NH 48321 42717) in the area of Beauly, Greens (NJ 81960 47587) in the area of New Deer and Netherton (NK 05761 45576) in the area of Peterhead; associated crossing works, temporary diversions and permanent realignment to 14.7 km of existing 132 kV and 275 kV OHLs, and ancillary development and associated works. This case will be determined by the Energy Consents Unit Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationDetails.aspx?cr=ECU00005221&T=5 using reference number ECU00005165