Planning applicationHLD/25/04267/SCRE

SSE Dundreggan Dam Glenmoriston Inverness IV63 7YJ

WithdrawnParking, Access & Highways
Official records · coverage in progress

2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.

Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

7 November 2025

Validated

7 November 2025

Planning Signals

3 detected traits

Specific
Access RoadsEia ScreeningSubstation
Application Insights

No form insights available yet.

AI summary

EIA screening for upgrading the access track to Glenmoriston Substation from Torgyle/Inverwick Road to the A887, supporting a new grid transformer.

Impact scale

Estimated scale of impact on the surrounding area.

5/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application HLD/25/04267/SCRE

SSE Dundreggan Dam Glenmoriston Inverness IV63 7YJ

WithdrawnParking, Access & HighwaysReceived The Highland Council

EIA screening for upgrading the access track to Glenmoriston Substation from Torgyle/Inverwick Road to the A887, supporting a new grid transformer.

Reference
HLD/25/04267/SCRE
Address
SSE Dundreggan Dam Glenmoriston Inverness IV63 7YJ
Status
Withdrawn
Category
Parking, Access & Highways
Impact scale
5/10
Authority
The Highland Council
Received
Validated
Last scraped
Record created
Latitude
57.177867
Longitude
-4.799912

Plain-language summary

EIA screening for upgrading the access track to Glenmoriston Substation from Torgyle/Inverwick Road to the A887, supporting a new grid transformer.

As filed with the council

EIA Screeing Request - Glenmoriston Substation - Upgrading the existing access track to the Glenmoriston Substation site from Torgyle in the west, which then becomes Inverwick Road and terminates at the A887. The upgrade is required to facilitate the delivery and installation of a new grid transformer and associated equipment.