1 / 4
Received

6 March 2026

Validated

10 March 2026

Planning Signals

4 detected traits

Specific
Associated InfrastructureSubstationWind TurbineWind Turbine Count 2
Application Insights

No form insights available yet.

AI summary

Plans for two large wind turbines with tall blades plus a new substation building and associated infrastructure.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application SHE/2026/052/PPF

Land To The East Of A970, Hill Of Wethersta, Shetland.

Pending ConsiderationRenewable Energy, EV & Heat PumpsReceived Shetland Islands Council

Plans for two large wind turbines with tall blades plus a new substation building and associated infrastructure.

Reference
SHE/2026/052/PPF
Address
Land To The East Of A970, Hill Of Wethersta, Shetland.
Status
Pending Consideration
Category
Renewable Energy, EV & Heat Pumps
Impact scale
8/10
Authority
Shetland Islands Council
Received
Validated
Last scraped
Record created
Latitude
60.3766
Longitude
-1.3339

Plain-language summary

Plans for two large wind turbines with tall blades plus a new substation building and associated infrastructure.

As filed with the council

The erection of 2 no. wind turbines (each with an generating capacity of up to 5MW), with a maximum hub height of 67 metres and a maximum blade tip height of 107 metres, and erection of substation building and associated infrastructure.