Planning application · AGB/26/01205/SCREEN
Screening opinion on extending a wind farm permission’s time limit.
Land East Of Kilmartin and North East Of Lochgilphead Argyll and Bute
Free preview. £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- Legal / Administrative
- Minor 2/10
- Section 42 Variation
- Wind Turbine
Overview
Why it’s worth watching
A screening opinion is sought to extend the build-out time limit for grid connection works tied to a consented wind farm.
- Today
- The existing permission has a three-year standard time limit.
- Proposed
- Change the time limit to ten years for completion of grid connection works.
- Stage
- Decided on 14 Jul 2026: Opinion Issued.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
This is a screening opinion for an application to change an existing permission, reference 22/01380/PP. It seeks to extend the standard time limit for completing the wind farm from three years to ten years, to allow time for grid connection works. The record says an opinion was issued; it does not state what that opinion concluded.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
1,438 of 1,612 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 174 records from that period are still being added or checked.
Proposals and decisions come from Argyll and Bute Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application AGB/26/01205/SCREEN?
Follow it on City Scope. This page is checked against the Argyll and Bute Council planning register and shows the latest status, decision and documents for AGB/26/01205/SCREEN. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the Argyll and Bute Council planning portal.
Set up a planning alertThe impact
What it involves.
Questions
What does “screening opinion” mean?
It is an opinion on whether the proposed change needs an environmental impact assessment. The record does not give the opinion’s conclusion.
Tags
- Section 42 Variation
- Wind Turbine
What each tag is based on
- Section 42 Variation
- ““Screening Opinion for Application under Section 42 … to vary the Standard Time Condition Limit … from three years to ten years””
- Wind Turbine
- ““application reference 22/01380/PP … to allow for completion of grid connection works to connect the wind farm””
Drawings
Where the site is.
On the map
Open the planning map →© MapTiler / OpenFreeMap © OpenStreetMap contributors
Where it’s at
The council has decided on 14 July 2026.
- Received13 Jul 2026
- Validated13 Jul 2026The council has everything it needs.
- Comments closed3 Aug 2026Usual deadline. Late comments may still count.
- Target decision13 Sept 20262-month target for local developments.
- Decision14 Jul 2026Opinion Issued.
The record
- Reference
- AGB/26/01205/SCREEN
- Address
- Land East Of Kilmartin And North East Of Lochgilphead Argyll And Bute
- Status
- Unknown
- Council decision
- Opinion Issued
- Decision issued
- Category
- Legal / Administrative
- Impact scale
- 2/10
- Authority
- Argyll and Bute Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.